How much deposit can a Florida contractor ask for?

Quick answer

Florida law doesn't cap the deposit amount, but it attaches strict duties once a deposit exceeds 10% of the contract price on residential work: the contractor must apply for the permit within 30 days of receiving your money and start work within 90 days after the permit is issued (Florida Statutes §489.126). Deposits of 10% or less carry no such deadlines.

Deposits are normal in construction — materials have to be ordered and crews scheduled before the first hammer swings. The question is what obligations come with the money, and Florida’s rules are specific.

The 10% rule (Florida Statutes §489.126)

For repair, restoration, improvement or construction on residential property, if a contractor receives an initial payment of more than 10% of the contract price, the law requires them to:

  1. Apply for the necessary permits within 30 days of receiving the payment (unless the work doesn’t need a permit), and
  2. Start the work within 90 days after all required permits are issued.

If they don’t, and they also fail to refund the money or complete the work after proper written demand, the statute treats it as a serious offense — it is one of the clearest protections Florida homeowners have.

What that means in practice

  • A deposit itself is legal at any amount the two of you agree to. The 10% threshold does not forbid larger deposits; it triggers the 30-day / 90-day duties.
  • Your protection kicks in at the permit. Once you’ve paid more than 10%, watch for the permit application within 30 days. No permit filed = a problem you can act on.
  • Get the schedule in writing. A good contract states the deposit, the payment milestones tied to real progress (e.g. “on delivery of windows,” “on passing final inspection”), and the balance due at completion.

A sensible structure

Reputable contractors tie payments to milestones so neither side carries unreasonable risk — for example, a deposit to secure materials, progress payments as phases pass inspection, and a final payment at completion. Avoid paying the full price up front under any circumstances.

If something goes wrong

Send a written demand (certified mail) to the contractor referencing §489.126. If they don’t respond, you can file a complaint with the Florida DBPR, which licenses and disciplines contractors statewide.

This page is general information, not legal advice. For a specific dispute, consult a Florida construction attorney.

Last updated November 3, 2026 · Applies to: All areas